T A Savery & Co Ltd

OleoOleo

Customer: T A Savery & Co Ltd

Location: Coventry

Requirement: To install digital CCTV cameras

Solution: Avigilon digital CCTV cameras

Services: Installation and ongoing support and maintenance

Customer’s View: “From reading some of the case studies on their website, it seemed as if they had an open minded attitude and a willingness to innovate, two things that were essential on this project. This impression was confirmed when I spent a morning with them discussing the project requirements. I was also reassured they were willing to invest that length of time with me exploring the possibilities and looking at options.” Paul Duffy, Diamond Ocean, technical adviser to Oleo

Using CCTV cameras in a record-breaking elevator safety application

Oleo International, a trading name of T A Savery & Co Ltd, is a leading expert in energy absorption technology.

Oleo has been producing energy absorption solutions for over 60 years and has over 1,000,000 units in circulation worldwide. In April 2015 the company was awarded the Queen’s Award for International Trade.

Oleo recently constructed the world’s tallest elevator buffer testing tower at its headquarters in Coventry. Elevator buffers sit at the bottom of an elevator shaft and are a vital last safety mechanism in the unlikely event that all other safety mechanisms fail. They work by absorbing the impact of the free falling elevator, saving the lives of the elevator’s occupants.

The 32 metre tower allows the company to conduct tests on buffers designed for the high speed elevators installed in the world’s tallest buildings.

The tower has already enabled Oleo to manufacture the world’s largest hydraulic elevator buffer. At 15 metres tall, the buffer can absorb the impact of an elevator travelling at 20 metres per second.

A challenging camera brief

Recognising the testing tower was an industry first, Oleo’s Marketing Manager Sandy Andringa wanted to record its construction to use in marketing activity. She commissioned freelance film maker Paul Duffy of Diamond Ocean, who had worked with the company previously, to investigate camera solutions.

Paul had a very clear brief: he was looking for a camera that could be used in two distinct ways. Firstly, a fully weatherproofed camera needed to be installed externally to produce footage that could be used in a time lapse film showing the tower’s construction.

Once construction was finished, that camera, along with two additional cameras, needed to be installed inside the tower so they could be used in a testing capacity. This would enable Oleo’s technical team to examine each elevator buffer test and, in the case of a problem, pinpoint exactly when it occurred and have access to valuable data to help solve it.

The key requirement for the external camera was that it could capture every element of the tower’s construction from top to bottom without needing to be repositioned. Given the tower’s height of 32 metres, this represented quite a challenge, although Paul soon realised that if a camera could be positioned in portrait orientation rather than the more typical widescreen landscape view, it would give the pictures required.

The key requirements for the cameras inside the tower were that they should give solid reliable performance at low light levels, because the tower does not have any windows.

Research led Paul to Avigilon cameras, which seemed to meet all the project’s diverse requirements. Further investigation led him to Ecl-ips, and he was immediately impressed by what he found. “From reading some of the case studies on their website, it seemed as if they had an open minded attitude and a willingness to innovate, two things that were essential on this project. This impression was confirmed when I spent a morning with them discussing the project requirements. I was also reassured they were willing to invest that length of time with me exploring the possibilities and looking at options.”

The combination of the quality of the Avigilon solution and the Ecl-ips approach was enough to convince Paul to recommend them both to Oleo. “I spoke to one or two other suppliers, but Ecl-ips offered the best option and I was happy to introduce them to Oleo.”

Once Ecl-ips had been contracted by Oleo, Ecl-ips’s technical team and Paul carried out camera and software tests to ensure the hoped-for results could be achieved. In the end, a 5MP camera was selected. This was mounted vertically and precisely positioned to give the best possible view of the entire construction site.

Paul was delighted with the attitude of the Ecl-ips engineer on site. “He demonstrated an ability to overcome challenges successfully and was clearly very engaged with the project and its unique elements, which made the process so much easier.”

Once the camera had been deployed, Paul downloaded the images from the camera every 24 hours. He supplemented the footage with footage from additional mobile cameras when other views were required and used them to create a time lapse film of the entire process.
Filming of the project in progress

oleo3

When construction was completed, the original camera was repositioned inside the top of the tower where the footage can be used to check the view from above. Two new 2MP cameras were positioned further down the tower where they can be used to check the quality of the test. As products of varying heights are tested in the tower, both new cameras are mounted on remotely-controlled, motor-driven pan/tilt units to allow more precise framing of each item under test. 

Oleo Company Video

The cameras are proving very effective, giving the Oleo technical team all the information that is needed during product testing.

Paul concludes, “The first stage of this project involved a single camera and Ecl-ips more than proved their worth. This meant we were happy to engage them in the second phase of the project to redeploy the original camera and deploy two additional ones inside the tower. The Ecl-ips technical team is now on hand to answer any queries and resolve any support issues raised by the Oleo IT team. All report that this relationship is working very well.”

Click here for more information on the cameras used for this project